FILES

RFP- C081- Hilltop Dr Storm Drainage

                    Improvements

August 7, 2024

August 26, 2024

DESCRIPTION:

This contract provides for approximately 186 LF of 12-inch CPSSP drainage pipe, approximately 144 LF of drainage swale, three catch basins, and two culverts. It will also resurface 1,200 SF of existing pavement, remove and replace 30 LF of chain link fences, install 38 LF of new chain link fence, and perform other related work. The engineer's estimate for this project is $70,865.00